Saturday, September 12, 2009

039. Back to the heat pump

There was a misunderstanding somewhere and it appears that the overall cost for the district heating system would exceed that of the version with a heat pump. I still don't understand this clearly so I obviously cannot explain it. So, it's back to the air-source heat pump, though perhaps not the one by Heliotherm.

I'm looking at some of the results of performance tests of these devices done by independent labs[1] to see if I find a favorite. One new issue that I've become aware of is that our technical room[2] is a little on the small side. The heat pump and its associated plumbing will fit, but we really could use the space if we can save it. Also, this type of installation requires large openings from the room to the outside and because this room is partly underground, construction elements called Licht- or Kellerschächte[3] have to be used. I have a great aversion to these things, partly from the maintenance point of view. To circumvent both these problems, I think a unit that is installed outside the house is called for (we had been considering only internal units so far). I have yet to find any indications that they're less effective than the ones installed inside.


[1] One such facility is in Switzerland → Wärmepumpen-Testzentrum WPZ.

[2] Here's a link to an old sketch → Figure 7g. The lower level.

[3] I'm not sure these things even exist in the same form in the Anglo-world. You can do an image search with the keyword "Kellerschacht" or "Lichtschacht" to see some examples.

Sunday, July 12, 2009

034. The one that got away

I should say: the one we let get away.

Once in a while, I like to look back at my collection of notes to see how things have come along since we embarked on this house project. I had mentioned before that our architects had originally (in November 2008) presented us with two distinctly different designs to choose from. In the interest of keeping complete records, here are a couple of drawings of the one that we decided against.

Figure 25a. Plan B upper level.
Figure 25b. Plan B lower level.

There were many things we liked in this plan, but in the end we happened to like the other one better. I would have selected this design if we had neighbors living closer to us. In that case, the secluded garden and courtyard would have been more desirable. What is not apparent in these drawings is that the garden and courtyard are actually on different levels (the stairs are not drawn in).

Given the particulars of our land, with the open southern exposure, we think that the design we chose (click here to go directly to the post where I discuss that) makes better use of it. I particularly like that all the rooms, including the main bathroom, have views out on that side.

Which one might you have chosen? Feel free to leave a comment.

Sunday, July 5, 2009

033. Choosing planners

Over the last few weeks, our architects — I'll refer to them as WA[1] from now on — collected bids from various planning firms for specific aspects of the house. It seems that construction activity around Switzerland, at least in the part where we live, is still quite intense and several of the companies that WA have worked with in the past decided not to submit bids for our project. Even so, WA made sure there were at least two bids in each category and we had a meeting last week to make the final selections. The categories we covered were as follows:

- the Bauingenieur: the people who calculate things like the statics of the building, in particular the parts in the ground which must be executed in concrete
- the Holzbauingenieur: the people who will do the details of how to construct the house in wood
- the HLS-Planer: Heizung (heating) Lüftung (ventilation) Sanitär (sanitation)
- the Elektroplaner: responsible for planning the electrical network

Once these "third-party" plans are in, they'll be sent out for bids from firms that actually do the work, such as build concrete structures and install plumbing. Meanwhile, WA are looking at every detail of the house and re-evaluating them, looking for the best solutions. New ideas are still being considered. I'll be giving updates here as things are finalized. We had not realized that so much designing would be done after the Vorprojekt (initial project) phase and I must say that we're really, really pleased with all the effort. This is our first experience working with architects and so far it has been excellent!


WA → Walker Architekten

Thursday, May 14, 2009

022. Approved

Figure 13. The stamp of approval.

A short update on what's been happening: Our building application has been approved by the local building commission. Now we get down to the real details.

Wednesday, April 1, 2009

015. The Baugesuch

Figure 9. The Bauprofile marks out the edges and corners of the building.

The application (Baugesuch or Baueingabe in German) for our building permit (Baubewilligung) was recently submitted to the local building commission. It includes blueprints of the house, plans for the connections to the water, sewer and electricity supply lines and an analysis of the energy usage (Energienachweis). In addition to these things one is also required to physically mark out the corners of the proposed building on the land as shown in figure 9 above. This is known as the Bauprofile (aka Baugespann or Bauvisiere and it allows the commission and other interested parties to visualize the building and easily ascertain that none of the building limits are exceeded. As part of the approval process a period of time, usually two or three weeks, is set aside to give the neighbors the chance to file objections or concerns. There's a form for this and the objections (Einsprache) have to be submitted in writing. Naturally, we're hoping that there will be none against our plans. It's an interesting process.

Monday, March 16, 2009

The wheels are in motion

Figure 7a. A rough representation of how the proposed house will sit on our land.

It was almost a year ago that we found a piece of land we liked and we initiated the process of acquiring it. We also started conversations with a selected group of Minergie-specialist builders in parallel. Back in those early days we were pretty sure that we would have one of these companies design and build our home. Their publicity materials assured us that they specialize in individual solutions and the combination of that with (i) the fixed-price guarantee they can offer and (ii) the good reputation for quality they enjoy is what interested us. As our discussions continued and we visited a number of houses they had built we realized that our individual solution would cost no less than what we could expect if we worked with an architect, with possibly a rather constrained design palette. We simply saw no examples that assured us that they would really build us something special. There was no doubt that they would build us a good, solid house, it was just that we were not convinced of their willingness to push the design envelope for us.

Figure 7b. The east elevation of our proposed house. Note how the land slopes off and the rear of the lower level is underground. The rectangular opening on the side is to the carport which is integrated into the building.

In the meantime I had compiled a short list of local architects based on examples of their work that I found either in magazines or through web searches[1] or actual houses I saw around our area. It was during this time that I decided that the websites of many architects left much to be desired[2]. In many cases the navigation is too cumbersome, the images miniscule or embedded in some fancy but slow-as-molasses display presentation, the information hardly useful. But there was one that stuck out for me. Both in the accessibility of the website and the aesthetics of the houses, especially the interiors.

Figure 7c. The north elevation. This is the side at street level. It looks a little menacing with the slits for windows. I'll say it: almost bunker-like. From the energy-loss point of view though, the north side (at these latitudes) is the worst and it makes sense to minimize glazing here. It's all made up for on the south side.

So one day at the beginning of last summer I plucked up my courage and popped into the office to make an appointment with said architect. Initially we had thought that we would want to talk with at least two architectural firms but we soon decided that we felt confident that this group would build us something lovely. So here we are now.

Figure 7d. West elevation. The door opens out from the kitchen. This side borders a public path connecting the two streets that can be seen on the map view so we'll have to have some sort of structure to provide privacy.

One of the wishes we conveyed to the architect was that we didn't want a "box". Boxes are very popular here right now, and it is true that they are more energetically favorable because the surface-area-to-volume ratio is lower than say, something enlongated. But, that's not the way we wanted to go. Actually, after our initial meeting where we set down our wants and desires and budget we were actually presented with not one but TWO very different plans. This was a very pleasant surprise. The version we decided against was also very interesting. It was more compact – it would probably have had better energy performance – and we felt it didn't make the most of the southern exposure of the land that we had. It also had a more complicated sunken-courtyard thing going on which was rather cool but we decided the simpler design would work better for us.

Figure 7e. The very important south elevation. This is where most of the solar gain will be made hence the plethora of windows. Here you can see the terraced garden on the left. The rest of the land we envision as a wildflower meadow, much as it has been until now.

It seems that issues of accessibility (as in this definition on Wikipedia) are on the minds of many people right now. It wasn't so different for us. We wanted a house where it would be possible to live on one level if necessary. So the upper floor at street level had to include a bedroom and a full bathroom.

Figure 7f. The upper-level floor plan.

A few words about the upper-level. The entrance hallway (A) can be closed off in the winter to reduce the infiltration of cold air. There's a built-in coat closet (B) with a glass inset on the stairwell side to let in light. The stairwell (C) is illuminated by a skylight. I haven't done the calculations yet (it's on my long to-do list) but my gut feeling is that a skylight provides more light per unit of heat lost through it than a similarly sized north-facing window[3]. The labels BF (Bodenfläche) and FF (Fensterfläche) refer to the areas of the floor surfaces and the window surfaces, respectively, in each room. There's a minimum ratio of 8:1 that is mandated for rooms in which people "live". As we have no real basement nor attic nor garage, we don't have many areas in which to accumulate stuff. There's a generous storage room (D) on this level which in combination with all the built-in wardrobes we have planned should cover all our storage needs and then some.

The division of the interior space was partly driven by my insistence on good natural light in all rooms, including bathrooms. Light shafts are frequently used to bring light into basement-type areas but I'm not a fan. This meant that on the lower level all the rooms had to be arranged on the south wall because all other sides lie underground, so to speak.

Figure 7g. The lower level.

The "technical" room is where the heating system, water boiler, air handling device etc will be located. It will be unheated and will lie outside the insulated hull of the house. Actually, the same is (obviously) true of the carport just above it.


[1] Many of the architects are listed through this website: www.swiss-architects.com

[2] I'm not alone in this. See this Guardian blog post from January of 2008: Why are architects' websites so badly designed?

[3] If you know I'm wrong, please explain why.